MMO Admin 856 Questions 9 Answers 0 Best Answers 1k Points View Profile0There are 5 steps involved when defining a project; which of the following is the last? MMO Admin Leader Asked: November 6, 2019In: Project Management0 ShareFacebook1 AnswerVotedOldestRecent MMO Panel 60 Questions 921 Answers 3 Best Answers 39 Points View Profile MMO Panel Expert Added an answer on November 6, 2019 at 10:39 AM a) Assign the cost account to a manager b) Code the WBS for tracking c) Assign the work package to a manager d) None of the aboveAnswer : (b) Code the WBS for tracking is considered as the last step for defining a project.0ReplyLeave an answerLeave an answerCancel reply Select file Browse Save my name, email, and website in this browser for the next time I comment.
MMO Panel
a) Assign the cost account to a manager
b) Code the WBS for tracking
c) Assign the work package to a manager
d) None of the above
Answer : (b) Code the WBS for tracking is considered as the last step for defining a project.